पत्रांक :11पीआर/06/2021 प्रेस विज्ञप्ति दिनांक: 11.06.2021
Set clear targets for Electrification and honor them : GM/ NCR
In tune with the Indian Railways vision of becoming net zero carbon emitter by 2030, a series of steps have been taken to promote environment friendly aspects in train operations. Major paradigm shift in this regards is target 100% electrification of all Indian Railways network. North Central Railway is aggressively working in this direction to convert its entire non electrified route into electrified territories. Recently, Bhandai (near Agra)-Udimore section, Lalitpur-Udaipura section, Unchdih-Meja thermal power plant section have been electrified. GM NCR Shri V.K. Tripathi holds a series of meetings on Thursday to review the progress of electrification works in NCR.
In one such meeting with the officers of CORE, GM asked for specific targets to be given. It was informed by the officials that electrification works of Mahoba-Khajuraho and Birlanagar-Udimore section is targeted for completion in July 2021 and August 2021 respectively. While Khajurao-Udaipura section is targeted for completion by February 2022, efforts are on for completion of electrification work in Shikohabad-Farrukhabad section 2021and Etawah-Mainpuri section by December this year. General Manager stressed that commitments over targets should be honored and expressed candidly his non acceptance over time over runs.
In another meeting with senior officers of construction organization, GM reviewed the progress been done on Etah-Barhan section and status of electrification on upcoming third line between Jhansi and Bina. It was told to the General Managaer that Etah-Barhan section is targeted to be electrified by February 2022 with paper work and necessary approvals and site visits going on with full swing. Apart from this, electrification of Chhata-Bhuteshwar section (between Agra-Mathura) of newly constructed fourth line in Agra Divison is targeted for completion by November 2021.
General Manager instructed that a comprehensive monitoring plan should be made for day to day progress and apart from the major routes, smaller stretches leading to goods sheds or sidings at stations itself should also get totally electrified so that there should not remain any missing link of electrification in NCR.The meetings were attended by Principal Chief Electrical Engineer Shri Satish Kothari, DRMs of Prayagraj, Jhansi and Agra divisions along with other headquarter and divisional officers.