Works Review Meeting organized at NCR headquarter

Works Review Meeting organized at NCR headquarter

More than 2000 o­ngoing projects discussed and reviewed


Two days' Works Review Meeting presided over by GM/NCR Shri Pramod Kumar concluded today at North Central Railway headquarter. During the marathon meeting a total of more than 2000 works in NCR were critically examined. The reviewed works included those of traffic facilities; passenger amenities; road safety works including Road Over Bridges, Road under Bridges; computerization; electrification; technology upgradation; track renewal among others.

General Manager while reviewing the works which have been physically completed and are yet to be closed o­n account of paper formalities, instructed to expedite the procedural formalities. The need to expedite the o­ngoing work was stressed by the General Manager. 

At the outset GM said that the quality of work should be of highest order and level of supervision needs to be the topmost.

Executing agency wise review of works was done with a threadbare analysis of feasibility issues, delays if any. Works reviewed included 681 works of DRM/Prayagaraj, 448 works of DRM/Agra, 452 of DRM/Jhansi , 257 works of Chief Adminisatrative Officer/ Construction and 322 works of other agencies.  

Principal Chief Engineer, North Central Railway Shri SK Mishra moderated the discussions while plan head coordinators apprised about the details and status of the works. While speaking o­n the financial health, Principal Financial Advisor Shri YK Shrivastava informed that there is no dearth of funds for infrastructure and safety works. 

The meeting was attended by the DRMs of Agra Shri Anand Swaroop, Jhansi Shri Ashutosh and Prayagraj Shri Mohit Chandra along with the Sr. Divisional Engineers(coordination).

From headquarters, the meeting was attended by AGM(in charge) Shri Kamlesh Shukla, CAO/C- Shri Sharad Mehta PCME- Shri Ajay Kumar Rana , PCCM- Shri Shashi Kant Singh, CPTM- Shri P.K Ojha, PCEE-Shri Satish Kothari, PCSTE- Shri M.K.Beura, PCSC- Shri Ravindra Verma, PCPO-Shri Awadhesh Kumar, CM(IT)-Shri Ankur Chandra and other senior officers.







  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.