ELECTICAL /General
OVERVIEW
1.1GENERAL INFORMATION
A.GAZZETTED OFFICERS - Sr. DEE/G/JHS, ADEE/G/JHS & ADEE/G/GWL.
B.Non – Gazette Staff
S.N. | Category | OSM group | TL/AC group |
S/S | O/R | S/S | O/R |
1 | Supervisors | 24 | 26 | 14 | 15 |
2 | Skilled | 110 | 112 | 136 | 121 |
3 | Un-skilled | 146 | 138 | 91 | 51 |
| Total | 280 | 276 | 241 | 187 |
C.Electrified Station:
Electrified/Non-electrified | Main line | Branch line | Total |
Electrified stations | 39 | 88 | 127 |
Non-electrified stations | 00 | 8 | 8 |
Total no of stations | 39 | 96 | 135 |
D.Maintenance depots:
Major maintenance depots for OSM | 07 JHS (East, West, Diesel Shed, DRM Building), GWL, ORAI, BNDA |
Minor maintenance depots for OSM | 04 (LAR, JUHI, CKTD & KURJ) |
Major maintenance depots for TL-AC | 02 (JHS & GWL) |
Minor maintenance depots for TL-AC | 02 (BNDA & KURJ) |
E.Power Supply System:
Sub-stations | 46 |
Transformers | 89 |
DG sets > 5KVA | 27 |
5 KVA DG sets | 28 |
G. Electrical Pumps:
S. N. | Type of pump | Qty |
1 | Vertical turbine pumps | 04 |
2 | Submersible pumps | 212 |
3 | Centrifugal pumps | 22 |
4 | Mono block pumps | 63 |
5 | Jet pumps | 02 |
6 | Sewage pump | 08 |
| Total | 311 |
H. Water Coolers:
S. N. | Water coolers | Qty |
1 | On platform | 77 |
2 | Offices & Others places | 112 |
| Total | 189 |
I. Train lighting & Air conditioning assets:
Rakes for Primary maintenance | 32 (BG/32) |
TL coaches | 344 (JHS/122, GWL/172 & KURJ/50) |
AC coaches | 122 (JHS/45, GWL/67 & KURJ/10) |
Power Cars | 10 (JHS/2 & GWL/8) |
Pre-cooling points | 274 (JHS/120, KURJ/20, BNDA/15, GWL/84, BAB/35 ) |
Battery charging sets | 374 (JHS/162, BAB/40, KURJ/30, BNDA/61 & GWL/81) |
J. Lifts and Escalators:
A.Existing Escalator over Jhansi Division
SN | Station | Location | Qty | Present status |
1 | JHS | PF No. 1 CSMT end | 1 | Escalator installed on 07.06.2015 |
PF No. 1 CSMT end | 1 | Escalator installed on 07.06.2015 |
PF No. 2/3 CSMT end | 1 | Escalator installed on 18.01.2018 |
2 | GWL | PF No. 1 NDLS end | 1 | Escalator installed on 25.12.2017 |
PF No. 2/3 NDLS end | 1 | Escalator installed on 12.12.2017 |
3 | LAR | PF No. 1 | 1 | Escalator installed on 31.07.2022 |
PF No. 2/3 | 1 | Escalator installed on 31.07.2022 |
B.Future Planning of Escalator over Jhansi Division
Name of station | Location | Qty | Executing agency for | Civil work progress with issues if any | Electrical work progress with issues if any | Availability of escalators | TDC |
FOB no. | PF no. | Civil Work | Electrical Work |
Jhansi | New FOB at NDLS end | 1 | 1 | Dy. CE/ Bridge line/JHS | Johnson | New FOB work is in progress by Dy. CE/BL/JHS. New FOB completion PDC : 31.07.2024 | PO issued on 14.11.2019 to M/S Johnson Lifts Pvt. Ltd. Chennai. Escalators arrived at site. Work will start after new FOB work. | 04 nos. escalators delivered on 29.06.2023 | 31.08.2024 |
1 | 1 |
2/3 | 1 |
4/5 | 1 |
MRA | New FOB | 1 | 1 | New FOB work not yet started by Dy. CE/Bridge Line/JHS | Work will start after FOB work. | Not delivered | - |
2 | 1 |
C.Existing lift over Jhansi Division
SN | Station | Location | Qty | Status of civil work | Status of Electrical work |
1 | JHS | PF No. 1 | 1 | Completed | Lift installed on 18.01.2019 |
PF No. 2/3 | 1 | Completed | Lift installed on 26.03.2021 |
PF No. 4/5 | 1 | Completed | Lift installed on 26.04.2022 |
2 | GWL | PF No. 1 | 1 | Completed | Lift installed on 17.07.2020 |
PF No. 2/3 | 1 | Completed | Lift installed on 06.01.2020 |
PF No. 4/5 | 1 | Completed | Lift installed on 06.12.2019 |
D.Future Planning of lifts over Jhansi Division
Name of station | Location | Qty | Executing agency for civil & electrical work | Civil work progress with issues if any | Electrical work progress with issues if any | Availability of lifts | TDC |
BNDA | PF-1 | 1 | Composite tender for electrical & civil work has awarded to M/s Arohi Elevators, Ranchi on 25.10.2022/ | Tiles finishing work is in progress. | 04 nos. lifts delivered at site. Electrical panel and changeover installed. Cabling work for providing power supply to lift completed. | Yes | Lift commissioned on dated 10.03.2024 |
PF -2/3 | 1 | Pit well foundation work & Structure erection completed. But the site is now infringing with doubling work hence, lift work at PF 2 stopped. | Yes | - |
KURJ | PF-1 | 1 | Tiles finishing work is in progress. | Yes | Lift commissioned on dated 15.03.2024 |
PF -2/3 | 1 | Tiles finishing work is in progress. | Yes | PDC of commissioning 30.03.2024 |
DAA | PF – 2 | 1 | Sr. DEN/N/JHS & Sr. DEE / G/JHS | LOA issued on 15.02.2024 | 04 nos. lifts will be procured through store. NS indent sent to HQ/Store. Tender published by HQ/store. Tender to open on 19.02.2024 | No | 30.06.2024 |
On extended FOB with 3rd line | 1 | No |
ORAI | - | 2 | Sr. DEN/C/JHS & Sr. DEE / G/JHS | LOA issued on 14.12.2023 | No |
K. Lighting Arrangements at LC gates in JHS Division
Type of Power supply | Total no. of LC Gate | Lights on LC Hut (Nos) | Lights on LC Gates on road (Nos) | Provision of Fan |
Lighting provided at Huts (both inside & Outside) | Lighting provided at huts (Only Inside) | Lighting provided at huts (Only Outside) | Lighting provided both side of track | Lighting provided only UP side | Lighting provided only Down side | Provided | Balance |
Solar | 166 | 166 | 0 | 0 | 166 | 166 | 0 | 166 | 0 |
SEB | 56 | 56 | 0 | 0 | 56 | 56 | 0 | 56 | 0 |
AT | 25 | 25 | 0 | 0 | 25 | 25 | 0 | 25 | 0 |
SEB & AT | 2 | 2 | 0 | 0 | 2 | 2 | 0 | 2 | 0 |
Solar & SEB | 28 | 28 | 0 | 0 | 28 | 28 | 0 | 28 | 0 |
Solar & AT | 17 | 17 | 0 | 0 | 17 | 17 | 0 | 17 | 0 |
Total | 294 | 294 | 0 | 0 | 294 | 294 | 0 | 294 | 0 |
L.Details of Solar Roof Top Plants in JHS Division
SN | Site Name | Capacity (kWp) | Status | Working | Not Working |
1 | DRM Office | 215.14 | Commissioned | 215.14 | - |
2 | Canteen | 5.04 | Commissioned | 5.04 | - |
3 | Railway Hospital | 55.44 | Commissioned | 55.44 | - |
4 | Electric AC Loco Shed (Old and new receiving yard) | 55.49 | Commissioned | 55.49 | - |
5 | Chattarpur | 10.08 | Commissioned | 10.08 | - |
39.84 | Commissioned | 39.84 | - |
6 | Khajuraho (Power house building + Station) | 18.9 | Commissioned | 18.9 | - |
25 | Commissioned | 25 | - |
7 | Dabra | 24.96 | Commissioned | 24.96 | - |
8 | Birlanagar Station | 32 | Commissioned | 32 | - |
9 | Datia Station | 10.08 | Commissioned | 10.08 | - |
10 | Morena Station | 19.84 | Commissioned | 19.84 | - |
11 | Tikamgarh Station | 24.96 | Commissioned | 24.96 | - |
12 | Sarkanpur Station | 24.96 | Commissioned | 24.96 | - |
13 | Gwalior Station | 440 | Commissioned | 640 | - |
200 | Commissioned |
Total Solar Capacity = 1204.93 KWp
Working = 1204.93 KWp