Electrical General

ELECTRICAL GENERAL SERVICE

Please click here to open PDF file


OVERVIEW

GENERAL INFORMATION


GAZZETTED OFFICERS - Sr. DEE/G/JHS, ADEE/G/JHS & ADEE/G/GWL.

Non – Gazette Staff


S.N.

Category

OSM group

TL/AC group

S/S

O/R

S/S

O/R

1

Supervisors

25

27

14

14

2

Skilled

139

98

156

93

3

Un-skilled

188

154

133

120

Total

352

279

303

227









Electrified Station:

Electrified/Non-electrified

Main line

Branch line

Total

Electrified stations

36

84

120

Non-electrified stations

02

14

16

Total no of stations

38

98

136







Staff Quarters:


Electrified staff quarters

4722



Maintenance depots:


Major maintenance depots for  

OSM

07 JHS (East, West, Diesel Shed, DRM Building), GWL, ORAI, BNDA

Minor maintenance depots for  

OSM

04 (LAR, JUHI, CKTD & KURJ)

Major maintenance depots for TL-

AC

02 (JHS & GWL)

Minor maintenance depots for TL-

AC

02 (BNDA & KURJ)











Power Supply System:


Sub-stations

46

Transformers

113

DG sets > 5KVA

30

5 KVA DG sets

27






Electrical Pumps:


S. N.

Type of pump

Qty

1

Vertical turbine pumps

04

2

Submersible pumps

286

3

Centrifugal pumps

24

4

Mono block pumps

83

5

Jet pumps

02

6

Sewage pump

07

Total

406











Water Coolers:


S. N.

Water coolers

Qty

1

On platform

120

2

Offices & Others places

105

Total

225






Train lighting & Air conditioning assets:


Rakes for Primary  

maintenance

20(BG/20)

TL coaches

435(JHS/206, GWL/188 & KURJ/41)

AC coaches

57(JHS/18, GWL/28 & KURJ/11)

Power Cars

04(JHS/1 & GWL/3)

Battery charging sets

28(JHS/13, KURJ/3, BNDA/01, GWL/ BG-11 )

Pre-cooling points

271(JHS/132, BAB/12, KURJ/20, BNDA/15 & GWL/(92)


 


Lifts and Escalators:


Existing Escalator over Jhansi Division


SN

Station

Location

Qty

Present status

1

JHS

PF No. 1 CSMT end

1

Escalator installed on 07.06.2015

PF No. 1 CSMT end

1

Escalator installed on 07.06.2015

PF No. 2/3 CSMT end

1

Escalator installed on 18.01.2018

2

GWL

PF No. 1 NDLS end

1

Escalator installed on 25.12.2017

PF No. 2/3 NDLS end

1

Escalator installed on 12.12.2017

 







Future Planning of Escalator over Jhansi Division


SN

Station

Location

Qty

Status of civil work

Status of Electrical

work

1

JHS

PF No. 1 NDLS end

1

New FOB work is in progress

PO issued on 14.11.2019 to M/S Johnson Lifts Pvt. Ltd. Chennai.

GAD of JHS escalator has been approved on dated 03.03.2021 & a copy of same has been hand over to Dy. CEE/Bridge line for making arrangement along with the new FOB.

PF No. 1 NDLS end

1

PF No. 2/3 NDLS end

1

PF No. 4/5 NDLS end

1

2

LAR

PF No. 1

1

Control room & canopy work is in progress.

Hoisting has been done, rest work is in progress

PF No. 2/3

1

Control room & canopy work is in progress.

3

GWL

PF No. 1

2

Not yet started. Further delay is due to station under SLDA

PO issued on 14.11.2019 to M/S Johnson Lifts Pvt. Ltd. Chennai.

 


















Existing lift over Jhansi Division


SN

Station

Location

Qty

Status of civil work

Status of Electrical work

1

JHS

PF No. 1

1

Completed

Lift installed on 18.01.2019

PF No. 2/3

1

Completed

Lift installed on 26.03.2021

PF No. 4/5

1

Completed

Lift installed on 26.04.2022

2

GWL

PF No. 1

1

Completed

Lift installed on 17.07.2020

PF No. 2/3

1

Completed

Lift installed on 06.01.2020

PF No. 4/5

1

Completed

Lift installed on 06.12.2019

 


Future Planning of lifts over Jhansi Division


Under Sugamya Bharat Abhiyan PB/1119/2020-21/NR), the proposal for 04 nos. of lifts at BNDA -02 nos. & KURJ – 02 nos. has been sanctioned in PH-53, FY 21-22. Detailed Estimate for 04 nos. lift has been vetted by accounts, Tender has been opened on 06.06.2022 and case has been discharged on 29.06.2022, re-tender is in process.


 


Lighting Arrangements at LC gates in JHS Division


Type of
Power supply

No of
LC gates

No of LC gates

No of LC gates (at Hut)

Both side

Only Up side

Only DN side

Hut both
side

Only
inside

Only outside

Solar

200

200

0

0

200

0

0

SEB

48

48

0

0

48

0

0

AT

45

23

20

2

45

0

0

SEB & AT

1

1

0

0

1

0

0

Solar & SEB

9

9

0

0

9

0

0

Solar & AT

2

2

0

0

2

0

0

Total

305

283

20

2

305

0

0


Details of Solar Roof Top Plants in JHS Division                 


SN

Site Name

Capacity (kWp)

Status

Working

Not Working

1

DRM Office

215.14

Commissioned

215.14

-

2

Canteen

5.04

Commissioned

5.04

-

3

Railway Hospital

55.44

Commissioned

55.44

-

4

Electric AC Loco Shed (Old and new receiving yard)

55.49

Commissioned

55.49

-

5

Chattarpur

10.08

Commissioned

10.08

-

39.84

Commissioned

39.84

-

6

Khajuraho (Power house building + Station)

18.9

Commissioned

18.9

-

25

Commissioned

25

-

7

Dabra

24.96

Commissioned

24.96

-

8

Birlanagar Station

32

Commissioned

32

-

9

Datia Station

10.08

Commissioned

10.08

-

10

Morena Station

19.84

Commissioned

19.84

-

11

Tikamgarh Station

24.96

Commissioned

24.96

-

12

Sarkanpur Station

24.96

Commissioned

24.96

-

13

Gwalior Station

440

Commissioned

640

-

200

Commissioned



Total Solar Capacity = 1204.93 KWp

Working = 1204.93 KWp


Work completed in last 03 financial years



SN

P/H

Name of work

1

36

JHS & GWL - Replacement of old fabricated tower by 20 mtrs high mast tower with LED.

2

36

JHS Div - Rewiring of railway station building & replacement of existing damaged pole.

3

36

JHS Div - Provision of LED lighting in railway residential quarters.

4

36

JHS & GWL - Provision of high tension over head lines by cable.

5

36

JHS- Replacement of old damaged panels & LT/UG cable and rewiring of DSL shed including LED lighting.

6

36

Augmentation of water supply system at 5 Station.

7

51

Replacement of lift at Divisional Railway Hospital at Jhansi.

8

64

Air conditioning of Running rooms at JHANSI and BANDA.

9

EnHM

Provision of New LED Facade lighting arrangement at Jhansi station.

10

EnHM

Improvement of illumination level as per Airport standard at all Stations over Jhansi division.

11

53

Provision of National flag at BNDA, CKTD, MCSC, DAA, LAR, MRA, BIX, MBA, SOE, TKMG, HAR and KURJ stations (12 nos)












Details of pending issues of the section for HQ assistance




  • To streamline the contract management, inventory management and attending to tender committee and selection committee meetings, one senior scale officer is essentially required in the electrical (G) branch.







Source : North Central Railways / Indian Railways Portal CMS Team Last Reviewed : 11-07-2022  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.